How GCs can cope with problem subs

How the government shutdown impacts construction contracts

This feature is a part of “The Dotted Line” series, which takes an in-depth look at the complex legal landscape of the construction industry. To view the entire series, click here.

When the government shuts down, contractors’ cash flow on federal sites does too.

The federal government shut down on Oct. 1, freezing activity on a number of construction sites. Attorneys say these shutdowns double as a stress test for how well construction firms document and negotiate their federal contracts.

During funding lapses, even short ones, the line between work continuation and work stoppage blurs. For some firms, that can mean weeks on site that go unpaid. For others, it’s a crash course in which clauses actually protect them when government operations grind to a halt.

Unclear funding

The most common surprise during a shutdown comes when contractors realize their agreements do not guarantee payment for work already performed, or that they must keep working anyway, said Zack Rippeon, partner in the Atlanta office of Adams & Reese.

Zack Rippeon

Courtesy of Adams & Reese

 

“Some may discover, for the first time, that they’re required to continue working even if they don’t get paid timely,” Rippeon told Construction Dive. “That discovery may require them to finance some, or all, of the work for extended time periods.”

If a project’s funding was appropriated before the fiscal year began, work can usually continue, albeit with slower payment cycles. But if funds were not secured before the cutoff, “it will go dark for the foreseeable future because no funds are available during the shutdown,” said Rippeon.

That uncertainty often extends to subcontractors too. Contractors who fail to flow down stop-work or suspension clauses to their subs risk being squeezed between the government and their project partners, said Michael Barnicle, partner at Atlanta-based Troutman Pepper Locke.

“Also, don’t presume there is a one-size-fits-all answer every contract because there are a variety of exceptions that may apply to certain contracts,” Barnicle added.

A documentation playbook

If a contractor’s government contact is already furloughed, firms must still provide written notice of any work freezes or cost increases, said Aron Beezley, partner at Birmingham, Alabama-based Bradley Arant Boult Cummings.

headshot of Aron Beezley

Aron Beezley

Courtesy of Bradley Arant Boult Cummings

 

“Government contractors should keep contemporaneous records of all communications, costs, delays and idle time,” Beezley told Construction Dive. “Contractors should also provide timely written notices to contracting officers under the contract’s changes or stop-work clauses.”

Tracking costs separately is critical, added Scott Damiecki, construction industry practice leader at CohnReznick.

“[Contractors should] stay in regular communication with the contracting officer and request written orders for stop-work or suspension of project,” Damiecki told Construction Dive. “Track all costs related to the shutdown such as demobilization, remobilization, idle time, storage, etc., as separate cost codes so you can quantify the impact.”

Proper documentation also extends downstream.

headshot of Scott Damiecki

Scott Damiecki

Courtesy of CohnReznick

 

“Provide proper notice to subcontractors to protect your own interest and preserve their rights,” said Damiecki. “Maintain detailed records of specific disruptions such as delays and stop-work orders. This should include information on the impact to employees which may include furloughs and layoffs.”

Navigate gray areas

Shutdowns often create confusion about whether work must continue, especially for partially funded projects. The result is a gray area where contractors fear both stopping and proceeding.

“The biggest vulnerability for government contractors is unclear funding and stop-work authority,” Beezley told Construction Dive. “Government contractors often lack definitive guidance on whether work can continue, or costs are reimbursable.”

Some contracts require continued performance regardless of payment status. That can force firms to self-finance operations until appropriations resume. Those without clarity risk disputes later, especially if subcontract agreements don’t flow down.

“For example, does the subcontract allow the contractor to demand the subcontractor continue performing, or provide for work stoppages or delayed payments?” Rippeon said. “And what damages are the subcontractors entitled to that the contractor may not be entitled to in such events?”

View the original article and our Inspiration here


Comments

Leave a Reply

Your email address will not be published. Required fields are marked *