The BIM mandate is being phased in over four years in the Republic of Ireland. From January 2024, it applied to the design team on projects worth more than €100m.
A year later, it was extended to contractors and the supply chain on projects worth more than €100m and to the design team on projects worth more than €20m.
This summer, it was extended again to contractors and the supply chain on projects worth more than €20m and to the design team on projects worth more than €10m. And in six months, it will be extended to contractors and the supply chain on projects worth more than €10m.