BIM gains ground in the Republic of Ireland

The BIM mandate is being phased in over four years in the Republic of Ireland. From January 2024, it applied to the design team on projects worth more than €100m.

A year later, it was extended to contractors and the supply chain on projects worth more than €100m and to the design team on projects worth more than €20m.

This summer, it was extended again to contractors and the supply chain on projects worth more than €20m and to the design team on projects worth more than €10m. And in six months, it will be extended to contractors and the supply chain on projects worth more than €10m.